On 29 Dec. 2015, two БКГ-2 electric diesel locomotives left CRRC Datong Works. They will run along “Silk Road” and pass through Baotou, Lanzhou, Urumqi and Central Asian countries, and finally arrive to Belarus in February 2016. Then will follow testing on the BCh network, and formal handing over to BCh is envisaged in August 2016. All other locomotives are scheduled for delivery before the end of 2016.
The contract of 18 electric diesel Locomotives was signed on 17 July 2013. БКГ-2 locomotive was awarded GOST in the middle of 2014. Up to now, the locomotive has completed the 251 domestic certification test items.
Track gauge 1,520 mm
Line voltage 25kV, 50Hz
Transmission AC-DC-AC
Wheel arrangement Co-Co
Axle load 25.0 t
Power rating 7,200 kW
Design speed 120 km/h
Start traction effort 570 kN
Min. curve negotiation radius 125 m
Length over coupler centers 22,960 mm
Ambient temperature -40℃~+40℃
Our company will develop three-axis bogies...
CRRC electric's first Public Open Day: technology tour of "Gigafactory"...
Five new maintenance products of the company have successfully passed the supervision and review and are qualified for mass production...
CRRC Taiyuan Company encounters the largest railway activity in the southern hemisphere...
D180-16 high power and high speed diesel engine has been developed successfully...